Reading List
TinyPilot: Month 20 from mtlynch.io RSS feed.
TinyPilot: Month 20
Highlights
- I hired TinyPilot’s first support engineer.
- I learned that hiring a support engineer is even harder than I expected.
- I’m evaluating platforms for paying international contractors.
Goal grades
At the start of each month, I declare what I’d like to accomplish. Here’s how I did against those goals:
Launch Voyager 2: PoE Edition
- Result: I finally launched Voyager 2 PoE
- Grade: A
Oh, boy. This took way longer than I expected. I looked back at the original design document that I wrote in early April 2021. I estimated that we’d have 200 units ready by May 15, 2021. In other words, I estimated six weeks, and it took 11 months.